Qpoint Liwan-Plot R017 construction photos
88 photos from 13 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R017 was built on the day of each visit.
9 January 2017100% built
10 August 201678% built
21 March 201672% built
29 November 201555% built
1 July 201553% built
18 February 201550% built
1 November 201446% built
17 July 201445% built
17 March 201444% built
13 August 201332% built
3 April 201315% built
9 September 201211% built
22 May 20126.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.