Qpoint Liwan-Plot R009 construction photos
84 photos from 13 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R009 was built on the day of each visit.
15 December 2016100% built
10 August 201681% built
20 March 201661% built
29 November 201556% built
1 July 201555% built
18 February 201551% built
1 November 201448% built
17 July 201445% built
17 March 201444% built
19 August 201331% built
8 April 201320% built
9 September 201212% built
22 May 20128.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.