Qpoint Liwan-Plot R008 A&b construction photos
54 photos from 6 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R008 A&b was built on the day of each visit.
19 April 201491% built
25 December 201390% built
18 August 201387% built
14 April 201375% built
20 November 201264% built
27 June 201276% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.