Living Legends Phase 3 construction photos

152 photos from 19 site inspections, newest first. The percentage is how much of Living Legends Phase 3 was built on the day of each visit.

8 May 2018100% built

15 February 201896% built

12 September 201791% built

14 February 201788% built

17 August 201683% built

21 June 201682% built

23 May 201681% built

28 September 201570% built

6 April 201568% built

28 December 201466% built

27 October 201461% built

17 August 201452% built

30 June 201448% built

9 March 201446% built

8 December 201341% built

19 August 201334% built

16 May 201326% built

20 November 201212% built

30 August 201210% built

Back to Living Legends Phase 3 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.