Living Legends Phase 3 construction photos
152 photos from 19 site inspections, newest first. The percentage is how much of Living Legends Phase 3 was built on the day of each visit.
8 May 2018100% built
15 February 201896% built
12 September 201791% built
14 February 201788% built
17 August 201683% built
21 June 201682% built
23 May 201681% built
28 September 201570% built
6 April 201568% built
28 December 201466% built
27 October 201461% built
17 August 201452% built
30 June 201448% built
9 March 201446% built
8 December 201341% built
19 August 201334% built
16 May 201326% built
20 November 201212% built
30 August 201210% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)