Living Legends Phase 2 construction photos
143 photos from 16 site inspections, newest first. The percentage is how much of Living Legends Phase 2 was built on the day of each visit.
12 September 2017100% built
17 August 201693% built
21 June 201692% built
25 April 201690% built
21 October 201577% built
28 December 201472% built
1 November 201467% built
5 August 201463% built
19 June 201456% built
9 March 201454% built
8 December 201346% built
19 August 201340% built
27 June 201337% built
4 April 201336% built
9 October 201225% built
13 June 201219% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.