85 photos from 10 site inspections, newest first. The percentage is how much of Port De La Mer - Le Soleil was built on the day of each visit.

7 January 2026100% built

23 October 202588% built

31 July 202582% built

2 May 202569% built

7 February 202558% built

21 September 202441% built

6 May 202414% built

27 July 20236.5% built

5 April 20233.9% built

29 December 20220% built

Back to Port De La Mer - Le Soleil construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.