Port De La Mer - La Sirene 2 construction photos
47 photos from 6 site inspections, newest first. The percentage is how much of Port De La Mer - La Sirene 2 was built on the day of each visit.
20 September 2024100% built
12 March 202481% built
24 August 202335% built
2 May 202320% built
19 January 20239.4% built
27 June 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.