Skip to content

The One Jbr construction progress

The register lists The One Jbr in Jumeriah Beach Residence - Jbr as complete, with a registered completion date of March 2020. Its last site inspection on record was in January 2020. The developer is The One Jbr.

100%

Built, at the site inspection of 22 January 2020

Construction complete

Registered completion date
March 2020
Construction started
September 2015
First registered
August 2015
Developer
The One Jbr
Community
Jumeriah Beach Residence - Jbr
Units
164
Escrow bank
Emirates NBD
Name in Arabic
ذا ون جي بي آر
Project number
1676
Site inspections
12

Schedule

The register lists The One Jbr as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 January 2020

100%+13 pts

  • The One Jbr construction site, inspection photo 1, 22 January 2020
  • The One Jbr construction site, inspection photo 2, 22 January 2020
  • The One Jbr construction site, inspection photo 3, 22 January 2020
  • The One Jbr construction site, inspection photo 4, 22 January 2020

21 August 2019

87%+12 pts

  • The One Jbr construction site, inspection photo 1, 21 August 2019
  • The One Jbr construction site, inspection photo 2, 21 August 2019
  • The One Jbr construction site, inspection photo 3, 21 August 2019
  • The One Jbr construction site, inspection photo 4, 21 August 2019

4 April 2019

74%+14 pts

  • The One Jbr construction site, inspection photo 1, 4 April 2019
  • The One Jbr construction site, inspection photo 2, 4 April 2019
  • The One Jbr construction site, inspection photo 3, 4 April 2019
  • The One Jbr construction site, inspection photo 4, 4 April 2019

14 November 2018

60%+12 pts

  • The One Jbr construction site, inspection photo 1, 14 November 2018
  • The One Jbr construction site, inspection photo 2, 14 November 2018
  • The One Jbr construction site, inspection photo 3, 14 November 2018
  • The One Jbr construction site, inspection photo 4, 14 November 2018

4 September 2018

48%+17 pts

  • The One Jbr construction site, inspection photo 1, 4 September 2018
  • The One Jbr construction site, inspection photo 2, 4 September 2018
  • The One Jbr construction site, inspection photo 3, 4 September 2018
  • The One Jbr construction site, inspection photo 4, 4 September 2018

12 April 2018

31%+11 pts

  • The One Jbr construction site, inspection photo 1, 12 April 2018
  • The One Jbr construction site, inspection photo 2, 12 April 2018
  • The One Jbr construction site, inspection photo 3, 12 April 2018
  • The One Jbr construction site, inspection photo 4, 12 April 2018

7 December 2017

20%+8.9 pts

  • The One Jbr construction site, inspection photo 1, 7 December 2017
  • The One Jbr construction site, inspection photo 2, 7 December 2017
  • The One Jbr construction site, inspection photo 3, 7 December 2017

14 June 2017

11%+2.1 pts

  • The One Jbr construction site, inspection photo 1, 14 June 2017
  • The One Jbr construction site, inspection photo 2, 14 June 2017
  • The One Jbr construction site, inspection photo 3, 14 June 2017
  • The One Jbr construction site, inspection photo 4, 14 June 2017

9 February 2017

9.1%+3.2 pts

  • The One Jbr construction site, inspection photo 1, 9 February 2017
  • The One Jbr construction site, inspection photo 2, 9 February 2017
  • The One Jbr construction site, inspection photo 3, 9 February 2017
  • The One Jbr construction site, inspection photo 4, 9 February 2017

20 October 2016

5.9%+0.9 pts

  • The One Jbr construction site, inspection photo 1, 20 October 2016
  • The One Jbr construction site, inspection photo 2, 20 October 2016
  • The One Jbr construction site, inspection photo 3, 20 October 2016
  • The One Jbr construction site, inspection photo 4, 20 October 2016

All 84 site photos, by inspection date

Own a unit in The One Jbr?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The One Jbr handover date?
Construction of The One Jbr is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The One Jbr?
The One Jbr was 100% built at the site inspection on 22 January 2020. The site has been inspected 12 times since January 2016. The Land Department took 84 site photos at its inspections.
Is The One Jbr delayed?
The register lists construction as complete.
Who is building The One Jbr?
The registered developer is The One Jbr.
Which bank holds the escrow account for The One Jbr?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.