81 photos from 8 site inspections, newest first. The percentage is how much of La Vie was built on the day of each visit.

8 September 2023100% built

10 May 202394% built

26 January 202387% built

23 June 202251% built

19 December 202127% built

21 March 20218.3% built

14 September 20206.2% built

6 May 20201.9% built

Back to La Vie construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.