Rosemont Residences construction photos

31 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Rosemont Residences was built on the day of each visit.

8 June 202643% built

2 February 202624% built

23 September 202513% built

3 June 20257.3% built

3 April 20240% built

Back to Rosemont Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.