Milestone Residences construction photos

50 photos from 6 site inspections, newest first. The percentage is how much of Milestone Residences was built on the day of each visit.

4 February 2026100% built

7 July 202570% built

30 May 202552% built

11 April 202536% built

13 February 202524% built

5 April 20240% built

Back to Milestone Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.