The One construction photos

140 photos from 15 site inspections, newest first. The percentage is how much of The One was built on the day of each visit.

8 November 2020100% built

13 August 202099% built

19 March 202098% built

4 September 201996% built

17 April 201991% built

14 November 201885% built

15 August 201877% built

18 April 201870% built

11 January 201857% built

28 September 201735% built

8 June 201731% built

19 January 201721% built

23 November 201614% built

15 June 20167.6% built

29 October 20152.3% built

Back to The One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.