57 photos from 6 site inspections, newest first. The percentage is how much of Stonehenge Residences 2 was built on the day of each visit.

24 February 2026100% built

7 November 202596% built

11 July 202586% built

26 March 202562% built

24 September 202423% built

13 July 20230% built

Back to Stonehenge Residences 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.