Sky Livings By Peace Homes construction photos
54 photos from 8 site inspections, newest first. The percentage is how much of Sky Livings By Peace Homes was built on the day of each visit.
24 July 202660% built
1 June 202652% built
14 January 202636% built
16 October 202530% built
23 June 202520% built
15 March 202513% built
30 June 20243.6% built
18 March 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.