Shamal Residences 2 construction photos

21 photos from 4 site inspections, newest first. The percentage is how much of Shamal Residences 2 was built on the day of each visit.

10 October 2016100% built

24 August 201699% built

1 October 201566% built

29 December 20146.0% built

Back to Shamal Residences 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.