Riviera Chalet construction photos

38 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Riviera Chalet was built on the day of each visit.

15 July 202675% built

26 March 202661% built

7 November 202540% built

27 March 202518% built

22 October 20242.7% built

1 August 20230% built

Back to Riviera Chalet construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.