Pulse Smart Residence construction photos
31 photos from 4 site inspections, newest first. The percentage is how much of Pulse Smart Residence was built on the day of each visit.
13 August 2017100% built
14 December 201693% built
14 April 201655% built
20 October 201523% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.