Plaza Residences construction photos

146 photos from 13 site inspections, newest first. The percentage is how much of Plaza Residences was built on the day of each visit.

4 March 2018100% built

29 August 201795% built

20 March 201791% built

12 December 201685% built

3 August 201679% built

23 March 201672% built

4 November 201565% built

31 May 201560% built

16 February 201554% built

11 November 201448% built

22 July 201447% built

29 March 201447% built

10 June 201347% built

Back to Plaza Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.