Park View Tower construction photos
113 photos from 11 site inspections, newest first. The percentage is how much of Park View Tower was built on the day of each visit.
17 November 2021100% built
5 May 202190% built
6 January 202180% built
12 October 202070% built
4 August 202060% built
15 June 202053% built
23 March 202044% built
6 May 201831% built
7 March 201821% built
14 August 20174.3% built
2 September 20151.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.