Oxford Terraces 2 construction photos

40 photos from 5 site inspections, newest first. The percentage is how much of Oxford Terraces 2 was built on the day of each visit.

20 November 2024100% built

29 August 202485% built

1 May 202457% built

14 November 202332% built

6 March 20232.1% built

Back to Oxford Terraces 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.