O 2 construction photos

70 photos from 8 site inspections, newest first. The percentage is how much of O 2 was built on the day of each visit.

12 September 2021100% built

28 February 202181% built

6 August 202054% built

27 January 202030% built

21 August 201918% built

13 March 20198.3% built

3 October 20186.4% built

20 June 20182.9% built

Back to O 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.