Neva Residences construction photos

73 photos from 7 site inspections, newest first. The percentage is how much of Neva Residences was built on the day of each visit.

11 March 2026100% built

13 February 202697% built

30 December 202595% built

22 July 202583% built

25 February 202553% built

31 August 20233.3% built

5 January 20230% built

Back to Neva Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.