Lodge Residences By Riviera Azure construction photos
26 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Lodge Residences By Riviera Azure was built on the day of each visit.
15 July 202663% built
27 March 202653% built
2 August 202525% built
13 February 20252.8% built
15 August 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.