La Riviera Estate construction photos

44 photos from 3 site inspections, newest first. The percentage is how much of La Riviera Estate was built on the day of each visit.

22 June 201494% built

12 January 201478% built

29 July 201367% built

Back to La Riviera Estate construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.