92 photos from 9 site inspections, newest first. The percentage is how much of Empire Residence was built on the day of each visit.

27 May 2024100% built

27 March 202497% built

15 May 202385% built

21 November 202270% built

20 June 202262% built

17 October 202147% built

21 January 201945% built

23 July 201837% built

23 January 201825% built

Back to Empire Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.