Elegance By Chaimaa Holding construction photos
51 photos from 5 site inspections, newest first. The percentage is how much of Elegance By Chaimaa Holding was built on the day of each visit.
10 March 2026100% built
28 January 202699% built
26 April 202428% built
18 December 202320% built
29 November 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.