Dezire Residences construction photos

39 photos from 5 site inspections, newest first. The percentage is how much of Dezire Residences was built on the day of each visit.

6 February 2020100% built

2 July 201874% built

5 November 201752% built

25 July 201743% built

2 November 201620% built

Back to Dezire Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.