Cubix Residences construction photos

60 photos from 7 site inspections, newest first. The percentage is how much of Cubix Residences was built on the day of each visit.

11 March 2026100% built

20 November 202595% built

29 July 202573% built

15 April 202555% built

5 October 202426% built

10 July 202415% built

25 October 20230% built

Back to Cubix Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.