Belgravia Heights II construction photos

73 photos from 10 site inspections, newest first. The percentage is how much of Belgravia Heights II was built on the day of each visit.

5 December 2024100% built

1 July 202482% built

25 January 202450% built

23 August 202336% built

11 May 202326% built

23 January 202320% built

27 July 20229.5% built

30 June 20197.2% built

25 October 20186.0% built

22 May 20184.1% built