76 photos from 10 site inspections, newest first. The percentage is how much of Avant Garde Residences By Skyline was built on the day of each visit.

24 August 2026100% built

2 July 202696% built

31 March 202686% built

30 December 202570% built

19 September 202559% built

24 June 202551% built

13 February 202530% built

30 October 202416% built

10 June 20243.7% built

11 October 20230% built

Back to Avant Garde Residences By Skyline construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.