Avalon Tower construction photos
131 photos from 13 site inspections, newest first. The percentage is how much of Avalon Tower was built on the day of each visit.
10 December 2020100% built
19 November 202098% built
14 September 202095% built
27 May 202086% built
26 February 202077% built
14 November 201960% built
28 July 201940% built
21 March 201920% built
10 February 201917% built
28 October 20189.2% built
24 July 20183.3% built
27 March 20181.1% built
11 December 20170.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.