1wood Residence construction photos

59 photos from 8 site inspections, newest first. The percentage is how much of 1wood Residence was built on the day of each visit.

8 July 202694% built

25 February 202689% built

10 October 202570% built

3 June 202556% built

30 January 202530% built

10 October 202411% built

3 June 20246.2% built

23 January 20240% built

Back to 1wood Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.