Jumeirah Park 7b&C construction progress

The register lists Jumeirah Park 7b&C in Jumeirah Park as complete, with a registered completion date of February 2016. Its last site inspection on record was in November 2018. The developer is Jumeirah Park.

100%

Built, at the site inspection of 6 November 2018

Construction complete

Registered completion date
February 2016
Construction started
June 2013
First registered
September 2013
Developer
Jumeirah Park
Community
Jumeirah Park
Units
194
Escrow bank
Mashreq Bank
Name in Arabic
حدائق جميرا -7b&C
Project number
1368
Site inspections
8

Schedule

The register lists Jumeirah Park 7b&C as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20142015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 November 2018

100%+12 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 6 November 2018
  • Jumeirah Park 7b&C construction site, inspection photo 2, 6 November 2018
  • Jumeirah Park 7b&C construction site, inspection photo 3, 6 November 2018
  • Jumeirah Park 7b&C construction site, inspection photo 4, 6 November 2018

2 August 2017

88%+4.4 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 2 August 2017
  • Jumeirah Park 7b&C construction site, inspection photo 2, 2 August 2017
  • Jumeirah Park 7b&C construction site, inspection photo 3, 2 August 2017
  • Jumeirah Park 7b&C construction site, inspection photo 4, 2 August 2017

27 March 2017

84%+3.7 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 27 March 2017
  • Jumeirah Park 7b&C construction site, inspection photo 2, 27 March 2017
  • Jumeirah Park 7b&C construction site, inspection photo 3, 27 March 2017
  • Jumeirah Park 7b&C construction site, inspection photo 4, 27 March 2017

1 November 2016

80%+5.3 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 1 November 2016
  • Jumeirah Park 7b&C construction site, inspection photo 2, 1 November 2016
  • Jumeirah Park 7b&C construction site, inspection photo 3, 1 November 2016
  • Jumeirah Park 7b&C construction site, inspection photo 4, 1 November 2016

19 July 2016

75%+8.1 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 19 July 2016
  • Jumeirah Park 7b&C construction site, inspection photo 2, 19 July 2016
  • Jumeirah Park 7b&C construction site, inspection photo 3, 19 July 2016
  • Jumeirah Park 7b&C construction site, inspection photo 4, 19 July 2016

4 May 2016

67%+11 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 4 May 2016
  • Jumeirah Park 7b&C construction site, inspection photo 2, 4 May 2016
  • Jumeirah Park 7b&C construction site, inspection photo 3, 4 May 2016
  • Jumeirah Park 7b&C construction site, inspection photo 4, 4 May 2016

14 October 2015

56%+11 pts

  • Jumeirah Park 7b&C construction site, inspection photo 1, 14 October 2015
  • Jumeirah Park 7b&C construction site, inspection photo 2, 14 October 2015
  • Jumeirah Park 7b&C construction site, inspection photo 3, 14 October 2015
  • Jumeirah Park 7b&C construction site, inspection photo 4, 14 October 2015

6 January 2015

44%

  • Jumeirah Park 7b&C construction site, inspection photo 1, 6 January 2015
  • Jumeirah Park 7b&C construction site, inspection photo 2, 6 January 2015
  • Jumeirah Park 7b&C construction site, inspection photo 3, 6 January 2015
  • Jumeirah Park 7b&C construction site, inspection photo 4, 6 January 2015

All 85 site photos, by inspection date

Own a unit in Jumeirah Park 7b&C?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Jumeirah Park 7b&C handover date?
Construction of Jumeirah Park 7b&C is recorded as complete, with a registered completion date of February 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Jumeirah Park 7b&C?
Jumeirah Park 7b&C was 100% built at the site inspection on 6 November 2018. The site has been inspected 8 times since January 2015. The Land Department took 85 site photos at its inspections.
Is Jumeirah Park 7b&C delayed?
The register lists construction as complete.
Who is building Jumeirah Park 7b&C?
The registered developer is Jumeirah Park.
Which bank holds the escrow account for Jumeirah Park 7b&C?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.