Viewz 2 By Danube construction photos
65 photos from 12 site inspections, newest first. The percentage is how much of Viewz 2 By Danube was built on the day of each visit.
20 October 202665% built
21 July 202650% built
23 April 202640% built
14 January 202630% built
28 October 202525% built
2 June 202520% built
28 January 202515% built
11 December 202411% built
23 April 20245.1% built
5 December 20230.4% built
16 May 20230% built
24 January 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)











.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)