Alandalus Building G construction photos
37 photos from 3 site inspections, newest first. The percentage is how much of Alandalus Building G was built on the day of each visit.
28 April 2021100% built
8 October 202096% built
4 December 201981% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.