Boutique 23 construction photos

32 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Boutique 23 was built on the day of each visit.

18 June 202649% built

24 February 202635% built

28 October 202525% built

25 June 202517% built

11 April 202513% built

7 December 20230% built

Back to Boutique 23 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.