Jebel Ali Village construction photos

106 photos from 14 site inspections, newest first. The percentage is how much of Jebel Ali Village was built on the day of each visit.

27 April 2026100% built

2 February 202696% built

9 October 202592% built

9 July 202582% built

30 April 202574% built

3 February 202561% built

3 July 202426% built

4 March 202410.0% built

24 October 20231.0% built

1 August 20230.3% built

31 March 20230.2% built

26 December 20220.2% built

27 September 20220% built

13 June 20220% built

Back to Jebel Ali Village construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.