Midtown - Dania construction photos

108 photos from 11 site inspections, newest first. The percentage is how much of Midtown - Dania was built on the day of each visit.

1 March 2020100% built

11 November 201991% built

21 July 201980% built

4 March 201968% built

17 October 201850% built

2 August 201840% built

8 April 201830% built

13 December 201712% built

31 July 20174.0% built

27 March 20173.5% built

29 November 20162.0% built

Back to Midtown - Dania construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.