Eaton construction photos

88 photos from 8 site inspections, newest first. The percentage is how much of Eaton was built on the day of each visit.

7 August 2024100% built

30 October 202395% built

24 July 202392% built

17 October 202292% built

20 January 202283% built

8 July 202156% built

13 November 201955% built

14 November 201633% built

Back to Eaton construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.