Eden Hills construction progress

The registered completion date for Eden Hills in Hadaeq Sheikh Mohammed Bin Rashid is December 2026. At the last site inspection, in September 2026, it was 3.5% built. The developer is Eden Hills.

3.5%

Built, at the site inspection of 22 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
March 2064
Construction started
March 2025
First registered
January 2025
Developer
Eden Hills
Community
Hadaeq Sheikh Mohammed Bin Rashid
Units
281
Escrow bank
Emirates NBD
Name in Arabic
ايدين هيلز
Project number
3311
Site inspections
5

Schedule

Between March 2026 and September 2026 the site added about 0.2 points a month. At that rate it would finish around March 2064, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 September 2026

3.5%+0.8 pts

  • Eden Hills construction site, inspection photo 1, 22 September 2026
  • Eden Hills construction site, inspection photo 2, 22 September 2026
  • Eden Hills construction site, inspection photo 3, 22 September 2026
  • Eden Hills construction site, inspection photo 4, 22 September 2026

23 June 2026

2.8%+0.5 pts

  • Eden Hills construction site, inspection photo 1, 23 June 2026
  • Eden Hills construction site, inspection photo 2, 23 June 2026
  • Eden Hills construction site, inspection photo 3, 23 June 2026
  • Eden Hills construction site, inspection photo 4, 23 June 2026

23 March 2026

2.3%+0.4 pts

  • Eden Hills construction site, inspection photo 1, 23 March 2026
  • Eden Hills construction site, inspection photo 2, 23 March 2026
  • Eden Hills construction site, inspection photo 3, 23 March 2026
  • Eden Hills construction site, inspection photo 4, 23 March 2026

18 July 2025

1.9%+1.9 pts

  • Eden Hills construction site, inspection photo 1, 18 July 2025
  • Eden Hills construction site, inspection photo 2, 18 July 2025
  • Eden Hills construction site, inspection photo 3, 18 July 2025
  • Eden Hills construction site, inspection photo 4, 18 July 2025

17 October 2024

0%

  • Eden Hills construction site, inspection photo 1, 17 October 2024
  • Eden Hills construction site, inspection photo 2, 17 October 2024

All 24 site photos, by inspection date

Context

Own a unit in Eden Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Eden Hills handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Eden Hills?
Eden Hills was 3.5% built at the site inspection on 22 September 2026. The site has been inspected 5 times since October 2024. The Land Department took 24 site photos at its inspections.
Is Eden Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Eden Hills?
The registered developer is Eden Hills.
Which bank holds the escrow account for Eden Hills?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.