Eden Hills construction progress

Eden Hills in Hadaeq Sheikh Mohammed Bin Rashid is 3.5% built at the Land Department inspection of September 2026. Developer Eden Hills. Completion registered for December 2026.

3.5%

Built, at the Land Department site inspection of 22 September 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
March 2064
Construction started
March 2025
Registered with the Land Department
January 2025
Developer
Eden Hills
Community
Hadaeq Sheikh Mohammed Bin Rashid
Units
281
Escrow bank
Emirates NBD
Name in Arabic
ايدين هيلز
Land Department project number
3311
Land Department site inspections
5

Schedule

Between March 2026 and September 2026 the site added about 0.2 points a month. At that rate it would finish around March 2064, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 September 2026

3.5%+0.8 pts

  • Eden Hills construction site, Land Department inspection photo 1, 22 September 2026
  • Eden Hills construction site, Land Department inspection photo 2, 22 September 2026
  • Eden Hills construction site, Land Department inspection photo 3, 22 September 2026
  • Eden Hills construction site, Land Department inspection photo 4, 22 September 2026

23 June 2026

2.8%+0.5 pts

  • Eden Hills construction site, Land Department inspection photo 1, 23 June 2026
  • Eden Hills construction site, Land Department inspection photo 2, 23 June 2026
  • Eden Hills construction site, Land Department inspection photo 3, 23 June 2026
  • Eden Hills construction site, Land Department inspection photo 4, 23 June 2026

23 March 2026

2.3%+0.4 pts

  • Eden Hills construction site, Land Department inspection photo 1, 23 March 2026
  • Eden Hills construction site, Land Department inspection photo 2, 23 March 2026
  • Eden Hills construction site, Land Department inspection photo 3, 23 March 2026
  • Eden Hills construction site, Land Department inspection photo 4, 23 March 2026

18 July 2025

1.9%+1.9 pts

  • Eden Hills construction site, Land Department inspection photo 1, 18 July 2025
  • Eden Hills construction site, Land Department inspection photo 2, 18 July 2025
  • Eden Hills construction site, Land Department inspection photo 3, 18 July 2025
  • Eden Hills construction site, Land Department inspection photo 4, 18 July 2025

17 October 2024

0%

  • Eden Hills construction site, Land Department inspection photo 1, 17 October 2024
  • Eden Hills construction site, Land Department inspection photo 2, 17 October 2024

All 24 site photos, by inspection date

Context

Own a unit in Eden Hills?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Eden Hills be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around March 2064. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Eden Hills is built?
3.5%, measured at the Land Department site inspection on 22 September 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Eden Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Eden Hills?
The registered developer is Eden Hills.
Which bank holds the escrow account for Eden Hills?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.