Mohammed Bin Rashid Al Maktoum City District One West - Phase 1 construction photos

89 photos from 10 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City District One West - Phase 1 was built on the day of each visit.

28 September 202693% built

25 June 202683% built

12 March 202673% built

4 December 202556% built

8 September 202540% built

11 June 202533% built

19 March 202520% built

25 November 20247.7% built

20 June 20240.1% built

9 June 20230% built

Back to Mohammed Bin Rashid Al Maktoum City District One West - Phase 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.