Belgravia Gardens construction progress
Belgravia Gardens in Falcon City is 3.1% built at the Land Department inspection of June 2026. Developer Ellington Karma Developers. Completion registered for September 2028.
3.1%
Built, at the Land Department site inspection of 4 June 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- April 2042
- Construction started
- January 2025
- Registered with the Land Department
- May 2025
- Developer
- Ellington Karma Developers
- Community
- Falcon City
- Units
- 743
- Escrow bank
- United Bank Limited
- Name in Arabic
- بلغرافيا جاردنز
- Land Department project number
- 3512
- Land Department site inspections
- 3
Schedule
Between February 2026 and June 2026 the site added about 0.5 points a month. At that rate it would finish around April 2042, more than three months after the September 2028 date registered with the Land Department.
Site inspections
4 June 2026
3.1%+1.8 pts
16 February 2026
1.3%+1.3 pts
28 January 2025
0%
Context
Falcon City has 2 projects under construction, 3.3% built on average.
Own a unit in Belgravia Gardens?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Belgravia Gardens be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around April 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Belgravia Gardens is built?
- 3.1%, measured at the Land Department site inspection on 4 June 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is Belgravia Gardens delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Belgravia Gardens?
- The registered developer is Ellington Karma Developers.
- Which bank holds the escrow account for Belgravia Gardens?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.