Villa Lantana 1 construction photos

83 photos from 12 site inspections, newest first. The percentage is how much of Villa Lantana 1 was built on the day of each visit.

21 August 2017100% built

14 May 201794% built

14 February 201786% built

27 September 201681% built

4 September 201680% built

24 May 201671% built

12 April 201667% built

25 October 201554% built

12 July 201545% built

17 May 201538% built

15 January 201532% built

13 August 20144.0% built

Back to Villa Lantana 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.