Yigo26 construction progress

The registered completion date for Yigo26 is December 2027. At the last site inspection, in July 2026, it was 1.1% built. The developer is Yangtze International Real Estate Developer.

1.1%

Built, at the site inspection of 21 July 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
March 2085
Construction started
December 2025
First registered
December 2025
Developer
Yangtze International Real Estate Developer
Units
190
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ايغو 26
Project number
4217
Site inspections
2

Schedule

Between November 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around March 2085, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 July 2026

1.1%+1.1 pts

  • Yigo26 construction site, inspection photo 1, 21 July 2026
  • Yigo26 construction site, inspection photo 2, 21 July 2026
  • Yigo26 construction site, inspection photo 3, 21 July 2026
  • Yigo26 construction site, inspection photo 4, 21 July 2026

18 November 2025

0%

  • Yigo26 construction site, inspection photo 1, 18 November 2025
  • Yigo26 construction site, inspection photo 2, 18 November 2025

All 6 site photos, by inspection date

Context

Yangtze International Real Estate Developer has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Yigo26?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Yigo26 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2085. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Yigo26?
Yigo26 was 1.1% built at the site inspection on 21 July 2026. The site has been inspected 2 times since November 2025. The Land Department took 6 site photos at its inspections.
Is Yigo26 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Yigo26?
The registered developer is Yangtze International Real Estate Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Yigo26?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.