Vue Doree construction progress

The registered completion date for Vue Doree is November 2028. At the last site inspection, in June 2026, it was 1.3% built. The developer is Crystal Bay Azure Development.

1.3%

Built, at the site inspection of 10 June 2026

Running behind its date

Registered completion date
November 2028
Finish at recent pace
April 2071
Construction started
November 2025
First registered
November 2025
Developer
Crystal Bay Azure Development
Units
50
Escrow bank
Mashreq Bank
Name in Arabic
فيو دوريه
Project number
4194
Site inspections
2

Schedule

Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around April 2071, more than three months after its registered date of November 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 June 2026

1.3%+1.3 pts

  • Vue Doree construction site, inspection photo 1, 10 June 2026
  • Vue Doree construction site, inspection photo 2, 10 June 2026
  • Vue Doree construction site, inspection photo 3, 10 June 2026
  • Vue Doree construction site, inspection photo 4, 10 June 2026

13 November 2025

0%

  • Vue Doree construction site, inspection photo 1, 13 November 2025
  • Vue Doree construction site, inspection photo 2, 13 November 2025
  • Vue Doree construction site, inspection photo 3, 13 November 2025

All 8 site photos, by inspection date

Context

Crystal Bay Azure Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vue Doree?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vue Doree handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2071. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vue Doree?
Vue Doree was 1.3% built at the site inspection on 10 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 8 site photos at its inspections.
Is Vue Doree delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
Who is building Vue Doree?
The registered developer is Crystal Bay Azure Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Vue Doree?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.