Vue Doree construction progress
The registered completion date for Vue Doree is November 2028. At the last site inspection, in June 2026, it was 1.3% built. The developer is Crystal Bay Azure Development.
1.3%
Built, at the site inspection of 10 June 2026
Running behind its date
- Registered completion date
- November 2028
- Finish at recent pace
- April 2071
- Construction started
- November 2025
- First registered
- November 2025
- Developer
- Crystal Bay Azure Development
- Units
- 50
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فيو دوريه
- Project number
- 4194
- Site inspections
- 2
Schedule
Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around April 2071, more than three months after its registered date of November 2028.
Site inspections
10 June 2026
1.3%+1.3 pts
13 November 2025
0%
Context
Crystal Bay Azure Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Vue Doree?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vue Doree handover date?
- The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2071. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vue Doree?
- Vue Doree was 1.3% built at the site inspection on 10 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 8 site photos at its inspections.
- Is Vue Doree delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
- Who is building Vue Doree?
- The registered developer is Crystal Bay Azure Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Vue Doree?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Globna By Crystal Bay AzureAlso by Crystal Bay Azure Development. 0%, Due September 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.