Vivida Residences construction progress

The registered completion date for Vivida Residences is September 2027. At the last site inspection, in August 2026, it was 0.8% built. The developer is N A M O Real Estate Development.

0.8%

Built, at the site inspection of 17 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
July 2102
Construction started
February 2026
First registered
March 2026
Developer
N A M O Real Estate Development
Units
66
Escrow bank
Emirates Islamic Bank
Name in Arabic
يفيدا ريزيدنسز
Project number
4168
Site inspections
2

Schedule

Between December 2025 and August 2026 the site added about 0.1 points a month. At that rate it would finish around July 2102, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

0.8%+0.8 pts

  • Vivida Residences construction site, inspection photo 1, 17 August 2026
  • Vivida Residences construction site, inspection photo 2, 17 August 2026
  • Vivida Residences construction site, inspection photo 3, 17 August 2026
  • Vivida Residences construction site, inspection photo 4, 17 August 2026

25 December 2025

0%

  • Vivida Residences construction site, inspection photo 1, 25 December 2025
  • Vivida Residences construction site, inspection photo 2, 25 December 2025

All 6 site photos, by inspection date

Context

Own a unit in Vivida Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vivida Residences handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2102. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vivida Residences?
Vivida Residences was 0.8% built at the site inspection on 17 August 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
Is Vivida Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Vivida Residences?
The registered developer is N A M O Real Estate Development.
Which bank holds the escrow account for Vivida Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.