Verdana 6 construction progress

The registered completion date for Verdana 6 is December 2028. At the last site inspection, in July 2026, it was 0.1% built. The developer is Reportage Plus A Real Estate Development.

0.1%

Built, at the site inspection of 22 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
July 2440
Construction started
December 2025
First registered
February 2026
Units
280
Escrow bank
Commercial Bank of Dubai
Name in Arabic
فيردانا 6
Project number
4288
Site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around July 2440, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 July 2026

0.1%+0.1 pts

  • Verdana 6 construction site, inspection photo 1, 22 July 2026
  • Verdana 6 construction site, inspection photo 2, 22 July 2026
  • Verdana 6 construction site, inspection photo 3, 22 July 2026

22 December 2025

0%

  • Verdana 6 construction site, inspection photo 1, 22 December 2025
  • Verdana 6 construction site, inspection photo 2, 22 December 2025
  • Verdana 6 construction site, inspection photo 3, 22 December 2025

All 6 site photos, by inspection date

Context

Reportage Plus A Real Estate Development has 16 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Verdana 6?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verdana 6 handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2440. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verdana 6?
Verdana 6 was 0.1% built at the site inspection on 22 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
Is Verdana 6 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Verdana 6?
The registered developer is Reportage Plus A Real Estate Development. It has 15 other projects under construction in Dubai.
Which bank holds the escrow account for Verdana 6?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.