Verdana 4 construction progress
Verdana 4 is 0.1% built at the Land Department inspection of July 2026. Developer Reportage Plus A Real Estate Development. Completion registered for September 2028.
0.1%
Built, at the Land Department site inspection of 22 July 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- June 2472
- Construction started
- September 2025
- Registered with the Land Department
- February 2026
- Units
- 306
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- فيردانا 4
- Land Department project number
- 4278
- Land Department site inspections
- 2
Schedule
Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around June 2472, more than three months after the September 2028 date registered with the Land Department.
Site inspections
22 July 2026
0.1%+0.1 pts
22 December 2025
0%
Context
Reportage Plus A Real Estate Development has 16 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Verdana 4?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Verdana 4 be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around June 2472. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Verdana 4 is built?
- 0.1%, measured at the Land Department site inspection on 22 July 2026. The Land Department engineers have inspected the site 2 times since December 2025.
- Is Verdana 4 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Verdana 4?
- The registered developer is Reportage Plus A Real Estate Development. It has 15 other projects under construction in Dubai.
- Which bank holds the escrow account for Verdana 4?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana 3Also by Reportage Plus A Real Estate Development. 0.1%, Due September 2028.
- Verdana Residence 3Also by Reportage Plus A Real Estate Development. 0%, Due September 2028.
- Verdana Residence 4Also by Reportage Plus A Real Estate Development. 0%, Due September 2028.
- Verdana 8Also by Reportage Plus A Real Estate Development. 0%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.