Varazze Tower construction progress

Varazze Tower is 92% built at the Land Department inspection of June 2026. Developer Olgana Real Estate Development. Completion registered for February 2024.

92%

Built, at the Land Department site inspection of 22 June 2026

32 months past its registered completion date

Completion date (Land Department)
February 2024
Finish at recent pace
January 2039
Construction started
September 2022
Registered with the Land Department
September 2022
Developer
Olgana Real Estate Development
Units
242
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فاراتسي تاور
Land Department project number
138
Land Department site inspections
14

Schedule

Varazze Tower was registered to complete in February 2024, 32 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around January 2039.

0%25%50%75%100%20142017202020232026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 June 2026

92%+1.2 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 22 June 2026
  • Varazze Tower construction site, Land Department inspection photo 2, 22 June 2026
  • Varazze Tower construction site, Land Department inspection photo 3, 22 June 2026
  • Varazze Tower construction site, Land Department inspection photo 4, 22 June 2026

19 September 2024

90%+10 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 19 September 2024
  • Varazze Tower construction site, Land Department inspection photo 2, 19 September 2024
  • Varazze Tower construction site, Land Department inspection photo 3, 19 September 2024
  • Varazze Tower construction site, Land Department inspection photo 4, 19 September 2024

1 May 2024

80%+4.3 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 1 May 2024
  • Varazze Tower construction site, Land Department inspection photo 2, 1 May 2024
  • Varazze Tower construction site, Land Department inspection photo 3, 1 May 2024
  • Varazze Tower construction site, Land Department inspection photo 4, 1 May 2024

5 December 2023

76%+0.7 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 5 December 2023
  • Varazze Tower construction site, Land Department inspection photo 2, 5 December 2023
  • Varazze Tower construction site, Land Department inspection photo 3, 5 December 2023
  • Varazze Tower construction site, Land Department inspection photo 4, 5 December 2023

24 June 2020

75%+0.1 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 24 June 2020
  • Varazze Tower construction site, Land Department inspection photo 2, 24 June 2020
  • Varazze Tower construction site, Land Department inspection photo 3, 24 June 2020
  • Varazze Tower construction site, Land Department inspection photo 4, 24 June 2020

11 March 2019

75%+4.8 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 11 March 2019
  • Varazze Tower construction site, Land Department inspection photo 2, 11 March 2019
  • Varazze Tower construction site, Land Department inspection photo 3, 11 March 2019
  • Varazze Tower construction site, Land Department inspection photo 4, 11 March 2019

13 August 2017

70%+9.1 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 13 August 2017
  • Varazze Tower construction site, Land Department inspection photo 2, 13 August 2017
  • Varazze Tower construction site, Land Department inspection photo 3, 13 August 2017
  • Varazze Tower construction site, Land Department inspection photo 4, 13 August 2017

5 December 2016

61%+18 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 5 December 2016
  • Varazze Tower construction site, Land Department inspection photo 2, 5 December 2016
  • Varazze Tower construction site, Land Department inspection photo 3, 5 December 2016
  • Varazze Tower construction site, Land Department inspection photo 4, 5 December 2016

30 May 2016

43%+11 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 30 May 2016
  • Varazze Tower construction site, Land Department inspection photo 2, 30 May 2016
  • Varazze Tower construction site, Land Department inspection photo 3, 30 May 2016
  • Varazze Tower construction site, Land Department inspection photo 4, 30 May 2016

21 January 2016

32%+6.8 pts

  • Varazze Tower construction site, Land Department inspection photo 1, 21 January 2016
  • Varazze Tower construction site, Land Department inspection photo 2, 21 January 2016
  • Varazze Tower construction site, Land Department inspection photo 3, 21 January 2016
  • Varazze Tower construction site, Land Department inspection photo 4, 21 January 2016

All 115 site photos, by inspection date

Context

Own a unit in Varazze Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Varazze Tower be completed?
The completion date registered with the Dubai Land Department is February 2024. At the pace of its recent inspections the site would reach 100% around January 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Varazze Tower is built?
92%, measured at the Land Department site inspection on 22 June 2026. The Land Department engineers have inspected the site 14 times since September 2013.
Is Varazze Tower delayed?
Yes. Its registered completion date of February 2024 has passed and the Land Department still lists it as under construction.
Who is building Varazze Tower?
The registered developer is Olgana Real Estate Development.
Which bank holds the escrow account for Varazze Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.