Tura Residence construction progress
The registered completion date for Tura Residence is April 2029. At the last site inspection, in July 2026, it was 0.7% built. The developer is Namat Real Estate Development.
0.7%
Built, at the site inspection of 13 July 2026
Running behind its date
- Registered completion date
- April 2029
- Finish at recent pace
- August 2103
- Construction started
- April 2026
- First registered
- February 2026
- Developer
- Namat Real Estate Development
- Units
- 23
- Escrow bank
- Emirates NBD
- Name in Arabic
- تورا رزيدينس
- Project number
- 4318
- Site inspections
- 2
Schedule
Between January 2026 and July 2026 the site added about 0.1 points a month. At that rate it would finish around August 2103, more than three months after its registered date of April 2029.
Site inspections
13 July 2026
0.7%+0.7 pts
7 January 2026
0%
Context
Own a unit in Tura Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Tura Residence handover date?
- The registered completion date is April 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2103. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Tura Residence?
- Tura Residence was 0.7% built at the site inspection on 13 July 2026. The site has been inspected 2 times since January 2026. The Land Department took 8 site photos at its inspections.
- Is Tura Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2029.
- Who is building Tura Residence?
- The registered developer is Namat Real Estate Development.
- Which bank holds the escrow account for Tura Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.